Cost of weekly bazaars rises due to delay
RAWALPINDI—The total cost allocated for the construction of 2 model
weekly bazaars has been enhanced due to delay in completion of work as
well as negligence of Capital Development Authority (CDA).
The PC-1 for the construction of model weekly bazaar of G-6 could not be
approved sofar, sources in the CDA said. According to the sources, the
construction work of 1400 stalls out of 1800 in weekly model bazaar of
G-6 have been completed while the estimated cost has been increased from
90 million to 140 million. The relevant authorities in CDA opined that
the cost has been increased followed by directions of Chairman Kamran
Lashari to include the area adjacent o Nullah in the bazaar. On the
other hand, the representative of Construction firm said that the bloody
military operation against administration of Lal Masjid, non approval of
PC-1 and non releasing of fund was prime reason behind the delay in
project. Meanwhile, sources said, H-9 weekly bazaar having 2600 stalls
would be completed by February 15 with total cost of Rs. 200 million
which was earlier 140 million.