|
Power
deficiency leaves WAPDA helpless
Bureau Report
LAHORE—Chairman WAPDA Shakil Durrani has said that load-shedding would
be overcome to a great extent by the end of current month. Addressing a
press conference at WAPDA House here on Thursday, he said, “We would be
able to overcome the current crisis in around 10 days. However, it would
take about three weeks to control the situation and by January 30 it
would be almost normal”.
Giving causes of the current crisis, he said, “Main transmission line of
Hubco of 500 KVA was seriously damaged by blasts on January 1 while
suspension in fuel supply due to riots following Benazir Bhutto’s
assassination compounded the situation.” WAPDA as well all Independent
Power Produces (IPPs) lack fuel storage facility and in case of
suspension of supply they are unable to operate their power generation
facilities.
He said that under rules IPPs should have sufficient fuel to meet their
demands for two weeks so that in case of any untoward situation they
continue their power generation operations. However, currently most of
them have fuel only to meet their demand for one or two days. “We have
approached government for issuance of notices to IPPs in this regard”,
told the Chairman.
He said a team of engineers has been sent which would repair the damaged
Hubco transmission line within two weeks restoring power supply. He said
another problem was that WAPDA was not getting required quantity of
natural gas, adding that effective steps have been taken in this regard
also and within a week 300 to 500 MW power would be provided through
this source also.
He said Kot Addu power plant would also start producing 600 MW power
within a week when it gets fuel supply from Karachi. He said power
demand in winter season during day time is 8500 MW while at night it
increases to 11500 MW. Currently power supply stands at 6500 MW, showing
shortage of about one third of total demand.
He said that by January 20 water release from Mangla and Tarbela
reservoirs would increase leading to increase in power generation by 600
to 1000 MW, adding that in case of rain the situation would further
improve. He said a meeting is going to be held tomorrow with high
officials of Railways, two gas companies and IPPs to discuss the ways to
avert any such situation in future.
He said that WAPDA officials have held meeting with traders bodies and
they are extending full cooperation to minimise affects of load-shedding
and appealed domestic consumers to show similar spirit by minimising
power consumption. To a question, he said, if Kalabagh dam had been
constructed, country would not have faced the current power crisis. He
said WAPDA suffer loss of Rs 100 million in Hyderabad area alone during
recent incidents of violence. He said three separate committees have
been constituted to look into the causes of the current situation and
make suggestions to ensure that such situation does not arise in future.
The menace of load shedding for 10 to 12 hours daily has once again
arrived to haunt the public even in winter times while the care taker
government has refused to accept any responsibility for the shortfall of
electricity and has emphasized that it is not responsible for the rising
inflation and the power crisis.
According to details, four to six hours load-shedding has become a
common practise since last many days in Federal Capital, Rawalpindi,
Multan, Faisalabad, Lahore, Karachi, Peshawar and other areas while on
the other hand skyrocketing gas prices have broken the back of masses.
WAPDA Sources told Online that as winters have arrived in the country,
demand of electricity has immensely increased to 12000 Megawatt (MW).
It has been told that Electricity deficit in the country has hit a
staggering 3,600 MW that has resulted in load shedding upto more than
six hours daily in various respective areas of the country. Similarly
WAPDA officials say that hydel-power generation hit an all time low at
1,300 MW against a peak summer generation of 6,600 MW due to a squeeze
on oil supplies and it generated 2,100MW against a summer supply of
2,900 MW. |