|
3 Gorges hydro-power project enters final year sprint
YICHANG—Construction of the
world’s largest hydro-power project at the Three Gorges in central
China’s Hubei Province has entered the final year sprint, with the
installation of remaining power generators ahead, said the construction
undertaker.
Cao Guangjing, deputy manager of the China Yangtze River Three Gorges
Project Development Corporation (CYRTGPDC) told Xinhua Thursday that the
work schedule for this year has been finalized and submitted to
authorities for approval.
“The main work of the hydro-power construction would be ready for state
checks by the end of 2008,” said Cao. Cao said that the water level of
the reservoir will be raised to 175 meters for the first time in
September this year, enabling it to exert a more decisive role in flood
control.
All of the 12 turbines on the right bank of the gigantic Three Gorges
project will be installed and put into use by December, leaving behind
only works of affiliated projects, such as the installation of shiplifts
and the building of an underground power workshop, scheduled for
completion in 2014 and 2010, respectively, said Cao.
The concrete placement of the 2,309 meters long and 185 meters high main
dam was completed in May 2006, when Cao announced that all of the
construction milestone throughout the project had been met ahead of
schedule, making it possible for the entire project to be completed a
year earlier than the scheduled 2009.
The 22.5-billion-U.S.-dollar project is the world’s largest water
control project, which recruited 26,000 people, including professionals
and specialists from 50-odd countries and regions, at the peak of its
construction. “Not many earthworks are left. Most of the workers have
departed the construction site. There are less than 2,000 workers here
now,” said Cao. China’s Three Gorges hydropower project generated 61.6
billion kilowatt-hours of electricity last year, about 25 percent more
power than in 2006, company sources said on Tuesday.
To date, the hydropower station had transmitted 207 billion kwh of
electricity to 11 provinces, municipalities and autonomous regions since
it started operation in July 2003. Currently, 21 turbines were
operational with a total installed capacity of 13.3 million kw. Five
more turbines would be added by year-end, according to its operator, the
China Three Gorges Project Corporation.
The 22.5 billion U.S. dollar project was launched in 1993 in the
mid-section of the Yangtze, China’s longest river. Originally, its plan
called for the 26 turbo-generators to produce 84.7 billion kwh of
electricity annually upon its scheduled completion in 2008.—Xinhua |