|
Design change
makes Baglihar unviable: India
NEW DELHI—In a severe jolt to the state of Jammu and Kashmir, the World
Bank-appointed neutral Swiss expert Raymond Lafitte has reportedly
ordered redesigning of the 450-MW Baglihar hydroelectric power project
on the Chenab river in Doda district and reduction of the dam’s height
by 1.5 metres.
Officials here are, however, taking solace in pointing out that the
expert rejected Pakistan’s demand to scrap the project on the ground
that it violated the Indus Water Treaty (IWT). The expert has also
turned downIslamabad’s demand of changes in the design of the main chute
spillways.
In the final meeting for arbitration in Washington early this week, the
officials said three specific changes recommended by the expert to meet
Pakistan’s objections would, however, make the project economically
unviable and as such a policy decision would have to be taken whether to
abandon or complete the project on which the government has already sunk
more than Rs 3.5 billions.
Lafitte, a former Swiss dam safety expert and professor electric power
plants and water resources development at Federal Institute of
Technology at Lausanne picked up by the World Bank to settle the
dispute, has called reducing the dam’s height by 1.5 metres, construct a
parapet wall of 1.2 metres and raise the power intake “cill” for
installation of turbines by three metres.
The last one has sent shivers to the project engineers as it would
involve redesigning of the entire structure and involves fresh model
studies. The project engineers insist that even small changes in the
design would bury the project but they were not able to say if the new
design would reduce the capacity to produce 450 megawatts of
electricity.
The Jammu and Kashmir Government, which is constructing the project,
does not want to give up easily. It plans to commission the National
Irrigation Research Institute of India’s prestigious Indian Institute of
Technology (IIT) at Roorkee, which had designed the original model, to
study the feasibility of changing the design and the extent it can be
changed to meet the prescriptions of Lafitte.
“We have already invested over Rs 3.5 billions and the total cost of the
project has already gone up to Rs 5.2 billions. The additional amount to
be incurred on the change of design would, however, make per unit cost
uneconomical,” the state government sources said. The project was beset
with problems right from inception and the state government had only
recently sought Rs 1 trillion from New Delhi to complete it. It will
require much more to meet the changes in the design.
The project was supposed to start power generation first by December
2005 and then by 2007. The new target also now seems impossible as the
Lafitte’s arbitration has given a setback of at least two
years.—Agencies
|