Progress on Munda, Kurram Tangi dam reviewed
Staff Report
ISLAMABAD—Federal minister for water and power Liaqat Ali Jatoi has said
that technical and feasible suggestion of all the stake holders would be
considered on the construction of mega water reservoirs in NWFP.
To review the progress of the commencement of the construction fo Munda
Dam and Kuram Tangi dam, he convened a high level meeting, which was
interalia attended by Interior Minister Aftab Ahmed Khan Sherpao,
Minister for Inter Provincial Coordination, Salim Saifullah Khan and
district Nazim Lakki Marwat, chairman WAPDA, MD PPIB, Chairman IRSA and
high officials from NWFP government.
The minister for Water and power said president and prime minister give
high priority to the development of water resources of the country and
have therefore decided to construct five large dams, including Kurram
Tangi Dam, Munda Dam by the year 2016. He added that the construction of
these dams is the need of the hour and we have to take hold and clear
out decisions in this regard. He also directed that the time schedule
for construction of mega water sector projects should be met without
delay.
The maters regarding height of Munda Dam, storage capacity, area to the
irrigated and hydro-power generated frm the dam were thoroughly
discussed in the meeting. The interior minister Aftab Ahmed Khan Sherpao
made a number of useful suggestions. The view point of government of
NWFP was also discussed in detail. It was decided that the dam should be
multi purpose like irrigation, flood mitigation and hydro-power to be
generation. A committee was constituted under the chairmanship of Member
(Water) WAPDA, comprising of representatives of PPIB, government of NWFP
and NESPAK to look into the technical aspects of the projects needed to
fix the height of the dam and other parameters to determined optimum
live storage etc and would submit its report within two weeks to the
Ministry.
The progress on Kuram Tangi Dam was also discussed and the government of
NWFP presented their view point on the project. The minister for
inter-provincial coordination Salim Saifullah offered a number of useful
suggestion to make the project more beneficial to the people of th area.
He was of the view that completion of the dam would bring green
revolution in NWFP especially in Southern area of the province which
would irrigate 0.362 MAF barren lands and to generate 83 MW electricity
and to help flood mitigation in the area.
The minister for water and power stressed importance of the project and
urged WAPDA to make every possible efforts to start work on the project
at the earliest for its timely completion. It was decided that WAPDA and
government of NWFP should hold a meeting on the hydraulic data
maintained by government of NWFP has been used for preparation of
detailed design of the project. A report in this account shall be
submitted to the ministry within a week.
On the request of NWFP government Jatoi also directed to shift the
office of Land Acquisition collector of WAPDA fom Mrdan to near the
sites of Kurram Tangi and Munda Dams. |